| Activity | Date |
| Draft survey questionnaire prepared | End of July 2015 |
| Draft semi-structured interview guides prepared | End of July |
| Draft party tools prepared | End of July |
| Ethical consent forms developed | July |
| Piloting (country teams) | August - September |
| Finalising and translating tools | September - November |
| Training of team for data collection | September - November |
| Field work | November 2015 - May 2016 |
| Transcribing, cleaning, translating | Alongside field work |
| Analysis workshop | 1-5 August 2016 |
| Data analysis | September 2016 - February 2017 |
| Write-shop | 5-9 February 2017 |
| Writing research outputs | February – August 2017 |
| Uptake activities at the international, national and local levels | May 2017 – ongoing, until end of project |
| Maintaining ethical consent forms | Throughout project, starting when fieldwork starts |