Activity | Date |
Draft survey questionnaire prepared | End of July 2015 |
Draft semi-structured interview guides prepared | End of July |
Draft party tools prepared | End of July |
Ethical consent forms developed | July |
Piloting (country teams) | August - September |
Finalising and translating tools | September - November |
Training of team for data collection | September - November |
Field work | November 2015 - May 2016 |
Transcribing, cleaning, translating | Alongside field work |
Analysis workshop | 1-5 August 2016 |
Data analysis | September 2016 - February 2017 |
Write-shop | 5-9 February 2017 |
Writing research outputs | February – August 2017 |
Uptake activities at the international, national and local levels | May 2017 – ongoing, until end of project |
Maintaining ethical consent forms | Throughout project, starting when fieldwork starts |